 19-May-2021
    On Wednesday-19-May  the Township of Teaneck started their repaving of Degraw Ave.  The section of road to be re-paved is from Queen Anne Rd to the border with Bogota. This is near Crestview St. in Teaneck. Contrary to earlier reports  E. Main St is not to be worked on at this time.  As of this afternoon the West bound lane of Degraw has been milled. 
   Work will continue through Friday-21-May. Paving is scheduled to take place on Monday-24-May. the work will run from 7:00a to 5:00p at the latest.  Due to the street plan the detour is set-up to direct traffic to E. Ft. Lee  to by-pass the construction. 
   Please plan alternate  routes during work hours. 